  1. The working group has evaluated all existing RES plans - What are its findings
  2. At the Ministry of Finance the detailed data in relation to the group of producers that may have had unexpectedly high revenues due to the increased purchase price
  3. Developing a methodology for a possible tax or levy

The working group set up between the Ministry of Finance (MoF), the Ministry of Energy, Trade and Industry (MoETI) and the Cyprus Energy Regulatory Authority (CERR) to examine the issue of potential excess profits of Renewable Energy Sources (RES) producers due to the unexpected increase in electricity prices, has undertaken the examination and evaluation of all existing RES schemes currently in place in Cyprus and their pricing. The working group has sent its findings, as well as detailed information, to the Ministry of Finance and is also considering the possibility of imposing a tax or fee.

Specifically, the working group has evaluated. [*]The Renewable Energy Project Scheme for household/enterprise own consumption RES projects using the offsetting method. [*]The Business/Public Buildings Self-Generation RES Project Plans. [*]The Renewable Energy Projects Projects for commercial purposes ending up in the competitive electricity market. [*]Renewable Energy Projects Projects in the context of the transitional market regulation ending up in the competitive electricity market.

As it follows from the conclusions of the working group, since the avoidance costs of the EEG are directly linked to the purchase price of RES electricity produced by the EEG, its unexpected increase, due to exogenous factors, inevitably led to an increase in the purchase price of RES.

Therefore, from the preliminary assessment of the above Plans and with the possibility of generating excess profits from RES generators, it is concluded that for the self-consumption plans (1, 2 and 3 as mentioned above), no excess profits are generated. On the contrary, the unanticipated increase in avoidance costs contributes to a reduction in RES and EE Fund expenditure, thus providing scope for additional financing of Fund projects that contribute to energy savings and promote the use of RES systems by households.

With regard to the commercial RES projects (4 above), due to the fact that the energy produced is priced on an avoided cost basis, the Working Group notes that the increased revenues of the projects in this Plan may have resulted, in some cases, in excess profits.

With regard to the commercial RES projects licensed under the transitional market regulation (5 above), it appears from the evaluations to date that any excess profit generation is limited.

In the context of the above findings, the working group has sent to the Ministry of Finance detailed information in relation to generators that may have had unexpectedly high revenues due to the increased purchase price of RES energy. From the further economic analysis of the data, the working group will proceed with the development of a methodology for a possible tax or levy on the generation of excess profits by RES producers and with an in-depth analysis of the data concerning the affected producers.