Today, April 14, 2022, the contract "Extraordinary measures for the protection of the coastal front in the area of Larnaca's Lighthouse of Peruvia" was signed. The Contract was signed, on behalf of the Government, by the Director of the Department of Public Works Mr. Antonis Koutsoullis and, on behalf of the Company C. Kasinos&Son Ltd, by the General Manager of the Company Mr. Costas Kasinos.
The Project is located in the marine area of Faros in Pervolia, Larnaca District and concerns the protection from marine erosion of a part of the coastal front with the placement of boulders.
The project covers a total length of approximately 435m. of the beach front in the sea area of Faros in Pervolia, Larnaca and includes the construction of natural boulders with a length of approximately 150m. and 14 boulders, of which 10 have a length of approximately 30m. each and 4 have a length of approximately 35m.m each, as well as the rehabilitation of an existing culvert (extension of an existing culvert Φ0,60m for about 10m) according to the drawings and all tender documents. The works are aimed at protecting the seafront from marine erosion in this part of the seafront. The works will be inspected by the Project Engineer, a representative of the Marine Works Branch of the Department.
The implementation of the project is planned to start in May 2022, with a duration of 12 months and a cost of €457.000.00 including VAT.
(MCI)
Contents of this article including associated images are belongs PIO
Views & opinions expressed are those of the author and/or PIO
Source