Signed today, Monday, August 8, 2022, at the Ministry of Transport, Communications and Works, in the presence of the Minister of Transport, Communications and Works, Mr. Nikos Nouris and the Director of the Department of Cadastre and Land Surveying, Mr. Elikos Elias, the Contract for the construction of the building of the headquarters of the Department of Cadastre and Land Surveying, with the method of Design, Construction and 12-year maintenance.

The Contract was signed, on behalf of the Government, by the Deputy Director of the Department of Public Works, Ms.

The Project concerns the Design, Construction and 12-year Maintenance of a reinforced concrete building (conventional construction), with a minimum total area of 12620m². The Project will be erected in the Municipality of Aglantzia, at the corner of Kyrenia and Glafkos Kleridis Avenues.

The works are expected to commence in September 2022 and will be completed in thirty-six (36) months. The defects and maintenance liability period is 12 (twelve) years from the relevant date to be stated in the Certificate of Acceptance of the entire project.

The cost of the project is €22,294,747.58 including VAT.

The Minister of Transport, Communications and Works Mr. Yannis Karousos stressed the importance of the project, as the State paid an amount of approximately €700 thousand per year for the rents of these premises. Mr. Karousos expressed his confidence that the project will be completed within the set timeframe. At the same time, he congratulated Mr. Nouris for the excellent cooperation as the two Ministries promote and execute projects in excess of €1.2 billion, whether they are road, urban planning or other infrastructure projects.

For his part, the Minister of Interior Mr. Nikos Nouris, expressed satisfaction that the Government's announcement to house the Governor's Services to avoid burdening the state budget with rents has been rolled out. In addition, Mr. Nouris said that with the completion of the project, it will not only facilitate the workers, but will also help to better serve the citizens as unnecessary travel will be avoided. At the same time, Mr. Nouris referred to the process followed, which has improved the architectural design and aesthetics.

Finally, he expressed his thanks to Mr. Karousos, the Director of the Land Registry, the Deputy Director of Public Works and the consortium.