The report of the Audit Service for the Ministry of Education on the year 2020 The most important findings identified What are the recommendations

Deficiencies and gaps are identified in the report of the Audit Service following an audit carried out at the Ministry of Education for the year 2020.

Specifically, as stated in the audit report released today, the purpose of the audit was to verify the correctness and regularity of samples of transactions of the Ministry of National Economy, selected on the basis of a specific methodology, as part of the audit aimed at expressing an audit opinion on the financial statements of the Republic of Cyprus.

During the individual findings of the financial audit, the following were noted:

a. Incomplete compliance with the provisions of the relevant Laws and Circulars of the GAO and the SO governing the granting of government grants.

b]b. Weaknesses and omissions in the monitoring of overdue receipts, as well as the monitoring and timely settlement of amounts booked in a segregated deposit account.

More specifically and always based on the EY report:

Sponsorships were granted to Public Legal Entities and School Boards (SEs) without following the established procedural framework regarding the management of sponsorships given to organisations with reserves, including bank balances.



"We recommended that the Ministry of Finance apply the provisions of the GL circulars for the purpose of granting state sponsorships, as well as the relevant YO circular, dd. 8.2.2012, regarding the management of sponsorships", says the EO.

It was also observed that the MoA did not take any actions to ensure that the ACs implement an efficient and effective internal control system, in accordance with the Law on Accounting and Financial Management and Financial Control of the Republic.

΅"We recommended that the Ministry of National Economy take the necessary actions to comply with the provisions of the Law, regarding the implementation of effective internal control systems in the ACs", notes EY.

At the same time, it was observed that amounts withheld from payments to contractors for construction projects remained outstanding for a number of years. Due to the accumulation of a large number of such balances and the lapse of a long period of time since the completion of the projects, it is difficult to consider whether they should be returned to the contractors or transferred to State revenues.

"We recommended that the Ministry of Public Works take appropriate action to settle the outstanding amounts," EY comments.

In conclusion, weaknesses and omissions were also found in the monitoring of overdue revenue, especially overdue tuition fees of the State Training Institutes (STIs).

"We pointed out the need to implement a satisfactory system of control and monitoring of the amounts collected from the various agencies of the Ministry of Public Works," the report concludes."