AHK informs residents of communities adjacent to the Vasilikos power station about upgrade projects at the Vasilikos Power Station
The environment is one of the key priority axes of AHK's strategy, the company said in an announcement.
In the context of transparency and continuous information of citizens living in the communities adjacent to the Vasilikos Power Plant, AHK informs the following:
Air quality around Vasilikos Power Station
Air quality around Vasilikos Power Station is measured and assessed in real time, 24 hours a day, through specialized Mobile Environmental Measurement Units, both by AHK and the Labor Inspection Department. These are located in the villages of Zygi, Kalavasos and Mari.
These environmental measurements are presented on the website of the Labour Inspection Department, Air Quality (https:/www.airquality.dli.mlsi.gov.cy/el), which any citizen can visit and monitor at any time. Based on the results shown on the website, the measurements are within the relevant limits set by the European Commission.
Installation of Environmental Protection Systems
As part of our strategy to continuously reduce pollutants and comply with the requirements of the Agency's Environmental Management System and the relevant European Commission Directives and Regulations, AHK has installed environmental protection systems such as dust retention, denitrification systems as well as desulphurization systems at the Vasilikos Power Plant Steam Units 1, 2 & 3.
Existing situation
The above systems have been installed in the Boilers of Steam Generating Units 1, 2 and 3 during the last 3 years or so. They concern denitrification systems and desulphurisation systems, and work has also been carried out to improve the performance of the previously installed electrostatic precipitators to reduce the solid dust particles emitted. The desulphurization system has experienced a number of technical issues affecting the operation of other auxiliary systems of the Boilers, resulting in their temporary shutdown.
Having contacted directly the construction companies of the Generating Units and based on the recommendations of these companies, AHK will proceed immediately to award the relevant contracts for the execution of the necessary corrective works.
Explanation of smoke colour
The white colour observed at the outlet of the flues of Boilers 1 and 2 is either due to excess combustion air/oxygen during periods of sharp load reduction, or the presence of water vapour in the flue gas due to the occurrence of steam in part of the Boiler systems, or due to the intake of atmospheric air at points in the flue gas system operating under negative pressure conditions.
At the same time, at times within 24 hours, dark-coloured smoke is observed from the flues of Boilers 1-3. This is part of the normal operation of the Boilers, and occurs either at times of sudden load increase of a generating unit (due to an unexpected shutdown of another conventional generating unit or a sudden decrease in RES production), or at times during the fumigation process in the three Boilers. It is noted that even with the anti-pollution technologies out of operation due to the technical issues encountered, the pollutant levels are similar to those before their installation.
Fuel quality used by AHK
It is AHK's standard practice that fuel is thoroughly tested upon receipt at the Vasilikos Power Station, both by AHK itself and by an independent, accredited laboratory to ensure that it is always within the required technical specifications.
Timetable for system repair
The desulphurization installations at Boilers 1, 2 and 3 have already been completed, while the completion of the desulphurization projects is being carried out gradually for all units on the basis of a specific binding timetable starting in autumn 2022 and completed in three stages as follows:
Unit 1: Spring 2023
Unit 2: Autumn 2023
Unit 3: Spring 2024