The procedures for the unfinished airport-Pafos road network have started to move The Ad Hoc Committee on Natura zones will meet at the end of September
The procedures for the airport-Pafos road network have started to "move", after the submission of the ecological assessment study, a site visit by the Environment Department will follow, while a meeting of the Ad Hoc Committee for the Special Ecological Assessment will follow, as Marinos Stylianou, Director of the Pafos EEB, told CNA.
According to Mr. Stylianou, on the part of the EEB, what should have been done has been done, since the study of the ecological assessment has been submitted some time ago. He pointed out that "towards the end of September, the Ad Hoc Committee on Natura zones will meet and among the topics on the agenda is the airport-Pafos road and its connection with the tourist area".
We expect before the Ad Hoc committee meeting that the Environment Department will come for a site visit, said the director of the Pafos EEB.
The fact that the project was stopped despite the river is due to the turn the whole project took, because of two pieces of land that were inserted in the special protection zones of the Natura network, Stylianou said. A firm position of the Paphos Chamber of Commerce and Industry is that this is a very essential infrastructure project for the city, he continued.
The road will connect not only the Paphos airport with the tourist area and with a road axis, which is very important, but also the tourist area with the rest of the coastal communities, he said. He added that this road will end up to Pegeia and Coral Bay.
According to Stylianou, the road project should have been completed by now, while he expressed hope that all obstacles related to the environment will be overcome, noting that they will await the views of the relevant departments.
Source: CNA
Contents of this article including associated images are belongs Cyprus Times