The Interior Committee called on the Ministry of Interior to immediately implement its commitments on the flood protection works in Larnaca
The issue of the construction of flood protection works for the protection of the Kamara and Vergina areas in Larnaca, addressed the work of the Interior Committee on Thursday, with MPs calling on the Interior Ministry to immediately implement its earlier commitments on the issue. As mentioned by EDEK MP Andreas Apostolou, the committee decided to send a letter to the Minister in this direction.
In his statements after the end of the discussion, DISY MP Prodromos Alabritis noted with satisfaction the position of the Ministry of Interior regarding the preparation of a draft proposal to the Council of Ministers for financing the project according to the study that has been prepared, adding that the study for the Vergina area, where there is a risk of reappearance of the phenomena, must proceed immediately.
He added that in the previous period some works were carried out by the Municipality of Larnaca and Aradippou, the provincial administration and the Drainage Council, which improved the situation , but there must be an acceleration of the studies and works to reduce the risk of flooding phenomena and protect the property of citizens.
AKEL MP Andreas Pasiourtides also noted with satisfaction today's decision of the Interior Committee to send a letter to the Minister of Interior in which he will set out the decisions taken by the Larnaca District MPs and the other members of the committee as a whole, as regards the construction timetables of the project, as the construction plans have been completed and the disbursement of the money to start the construction is still to be made.
"We keep the verbal commitment of the Minister of Interior one day after the floods that he will take the issue directly to the Council of Ministers for approval of the 4-5 mln." adding that they want in writing the exact timeline for disbursement of the instalments so that the contracting authority can also go out to bid for the commencement of the works.
For his part, DIKO MP Christos Orphanides said that the necessity of completing the flood protection project in Kamares has not been understood. Orphanides, while appealing to the parties involved to meet and within 15 days to come up with specific proposals that will reassure the concerns of the citizens and those who are interested and sympathize with the anguish of the residents of the area.
ELAM MP Sotiris Ioannou said that the problem of flooding in Larnaca province is real, with citizens not caring who is responsible when their property is threatened, adding that the Larnaca MPs have jointly asked the Ministry of Interior to express its practical political will to solve this major problem.
EDEK MP Andreas Apostolou said that the Kamares projects were a political commitment given to Larnaca since 2014, shortly after the start of the current government, which has not been implemented to date, a few months before the end of its second term.
He added that given the communication of the Minister of Interior with the Mayor of Larnaca, to whom he expressed his willingness to proceed with the implementation of the commitment, and the unanimous decision of the Interior Committee today, a letter will be sent to the Minister of Interior requesting that his commitment to Larnaca for the implementation of the specific project of about €5 million be immediately brought to the Council of Ministers for approval and an amendment to the budget of the Ministry of Interior is expected to be submitted so that it At the same time, the rest of the works concerning the residential area more of Aradippou Municipality in the Vergina area, which is not covered by the first phase of the project, should proceed and a way should be found to cover the area because the residents are interested in protecting their properties," he said.
He added that the first phase of the project amounts to €5 million, with the total cost estimated at €14-15 million, and in case of a written commitment from the Ministry that funding is available, the Municipality will accept bids until the end of the year, with the project starting around March with an implementation period of 18 months. in flood protection projects, has secured another 18 million from the Recovery Fund, four more major flood protection projects are starting within the year and will continue with 3-4 more projects in 2023 and 2024, for a total amount of €18 million.
Pissouri support project success uncertain according to ETEK, says Attalidou
Alexandra Attalidou, Member of Parliament for Citizens' Ecological Cooperation, referred in her statements to the issue of project planning in Cyprus in general, referring to sloppiness and inability of the state to plan properly so that there are no consequences afterwards.
Apart from the problem of flooding in Larnaca, Ms. Attalidou also referred to the problems created by the ongoing retreat of the subsoil in the Pissouri community, arguing that the state is responsible for this situation, while she said that according to the ETEK it is not certain whether the soil support project in Pissouri will be effective, as there is a 50% chance that the support will fail, and that there should be time between the first and second phase to carry out the studies and measurements that would confirm whether the project will be effective.
"The state cannot spend millions if there are doubts about whether the project will stop the problem that exists and threatens the properties and lives of residents," he said, adding that any future developments should take climate change into account.
Source: CNA