What the Auditor General says about the Limassol stadium
The Auditor General gives his position on the issue of the construction of the Limassol stadium and what has been said and written in recent days.
In a post on social media, he quotes data from the Audit Service's Report on the CAA, in a report dated 15.6.2018.
According to the Auditor General, he says it is "evidence that shows that the construction process of the Limassol stadium started wrong from the beginning, with an initial budget of €15m for 12,000 spectators."
[BR][BR]Evidence from an EY Report on the CMO dated. 15.6.2018, showing that the construction process of the Limassol stadium started wrong from the beginning, with an initial budget of €15m for 12,000 spectators. pic.twitter.com/RAAx19JfEp
- Odysseas Michaelides (@OMichaelides) February 2, 2022
Opens debate on Limassol Arena in Parliament
DIKO MP Chrysanthos Savvidis, said that the issue concerning the allocation of the funds approved for the construction of the Limassol Arena stadium in Kolossi was raised as an ex officio matter before the Education Committee.
"They were building a stadium 13.000 seats and in the end we learn that there will be less seats," he said, adding that €40 million has already been approved for the stadium and another €10 million for the road network around it
"These amounts were approved for a project that in the end seems to be different from what we had in mind," he concluded.
With information from CNA