The progress of the implementation of the works for the improvement of Kappari Avenue in Paralimni was inspected today by the Minister of Transport, Communications and Works, Mr. Theodore Pyrillis.
The improvement works on Kappari Avenue started in September 2021, with an execution period of 24 months (partial project execution) and a cost of approximately €7.7 million including VAT.
The improvement works on Kappari Avenue started in September 2021, with an execution period of 24 months (partial project execution) and a cost of approximately €7.7 million including VAT. Specifically, the project concerns the northernmost part of Kappari Avenue and the new road network consists of the main road network with a length of 2.07 km and the secondary road network with a length of approximately 1 km.
The main road network includes two lanes with parking spaces on both sides (parallel parking), paved sidewalks, green lanes on both sides, a 2.60 m wide bicycle lane on the right side of the road, pedestrian crossings and bus stop bays. A new roundabout will be built on the last 250 metres or so of Kappari Avenue. The secondary road network consists of two lanes with sidewalks. In Yiorki Papadopoulou Street, a bicycle lane is also being constructed on the north side of the road.
During his visit to the site where the works are being carried out, Mr. Karousos expressed his satisfaction with the progress of the works, noting that Kappari Avenue is a basic urban road infrastructure for the Municipality of Paralimni and its improvement is expected to upgrade the area functionally, qualitatively and aesthetically, better serving both the residents of the free Famagusta District and visitors.
(MKY)